Tuesday 18 August 2020

DESIGN PROCESS OF MV LINE

 DESIGN PROCESS

Typical steps in an overhead distribution line design are shown below. The actual steps and their sequence will depend upon the individual project and the context in which the design is performed.

The process is iterative, with the designer making some initial assumptions, e.g. as to pole height and size, which may later need to be adjusted as the design is checked and gradually refined. The optimum arrangement that meets all constraints is required as the final outcome. Utility Power uses overhead line simulation software to aid the design process.

Determine Design Inputs

Prior to commencing design, it is important to collect and document all relevant design inputs. This may include:

a) planning reports, concept, specification or customer request for supply initiating the project;

b) load details, disturbing loads etc;

c) special requirements of customers or stakeholders (e.g. supply reliability);

d) system planning requirements;

e) information about possible future stages or adjacent developments, road widening or other;

f) applicable relevant standards and statutory requirements;

g) co-ordination with other utilities - 'Dial Before You Dig' results

h) co-ordination with road lighting design;

i) survey plans or base maps;

j) any site constraints identified and

k) environmental factors (as elaborated below)

The designer should take into consideration the environmental factors which could influence the design of the supply arrangement, e.g. selection of and location of equipment, etc.

For example, suppose an overhead MV line is to be constructed to supply a customer remote from a zone substation, and the line route traverses an area of high lightning activity. It would seem prudent for the designer to include an earth-wire system to shield the conductors, in the line design, even though this is not normal practice for distribution lines.

Similar considerations should apply for lines or installations close to the coast, which are subjected to high salt-pollution levels. High pollution insulators may be incorporated in the line design.

Consideration must be given to the location of the equipment or the environment the equipment is to operate in. For example, a pole top transformer may not be entirely suitable for use outside a cement plant or quarry, where the build up of fly-ash or dust on insulators may lead to nuisance tripping or a disproportionately high level of maintenance. Others include mines sites, with open air blasting, etc.

Consideration shall also be given to:

• Cultural Heritage and Native Title;

• Environmental approvals for clearing or removal of native vegetation; and

• Siting of Substations with respect to Noise Control.

Current statutory processes require a range of approvals to be obtained prior to commencement of works. Due to the time taken to obtain these approvals, these issues must be considered at the commencement of a project.

As per the Western Australian Distribution Connections Manual (WADCM Section 6.12) environmental and heritage impacts must be investigated and managed by the applicant for power supply and their agent. Issues may include but are not limited to the following:

a) Aboriginal heritage sites and objects of suspected aboriginal origin;

b) Acid sulphate soils;

c) Bio-security weeds, pests and disease spread (e.g. dieback disease);

d) Declared rare flora and threatened ecological communities;

e) Dust;

f) Erosion;

g) Land entry permits;

h) Native title;

i) Noise;

j) Protected wetlands;

k) Vegetation clearing permits; and

l) Waste management including controlled waste.

The design should be 'traceable' back to a set of design inputs. Persons other than the original designer should be able to review the design and see why it was done a certain way.



Monday 17 August 2020

Pre – Line Design Considerations

 Pre – Line Design Considerations

There are certain basic requirements that have to be considered when designing overhead distribution power lines. These requirements fall within the broader National Standards and Guidelines (e.g. AS 7000). This blog has been put in place to facilitate the development of innovative project designs that will aim at:

(a) Reduced cost to customers;

(b) Reduced Life Cycle ( Maintenance) costs;

(c) Greater durability with due consideration to location in a cyclonic areas;

(d) Safety of workers and the General Public;

(e) Environmental Compatibility;

(f) Electromagnetic Field Compatibility;

(g) Favorable public acceptance ( aesthetics); and

(h) Increased network safety and reliability

When the requirement for a line has been established, the following factors need to be considered before the design can commence. They are:

a) Potential number of Customers and total load;

b) Estimation of potential load growth;

c) Availability/ and or requirement for interconnections;

d) Selection of Voltage for line operation;

e) Size and location of loads (Bulk supply, transformers)

f) Selection of Route

g) Length of line

h) Life Cycle costs

Introduction to Design of Distribution Overhead Power Line

Dear Readers the following blogs will be about designing distribution overhead power lines

So be with us to learn more have a good Read!!!

General

This blog describes the engineering process involved in designing distribution overhead power lines. These lines typically originate from Zone substations as Medium Voltage lines and are stepped down to Low Voltage through distribution transformers. Low Voltage overhead power lines then transmit power from transformers to customer installations. Some customers are supplied directly from the Medium Voltage network.

Overhead Power lines account for a significant proportion of  Power networks. These assets involve large amounts of capital expenditure, both by utility Power and customers. Also, these lines need to be properly designed and constructed and it is imperative that a high level of engineering input is put into their designs, particularly because these lines may be built in cyclonic areas. Effort expended here could avoid unnecessary expenses for utility Power and customers and ensure that the customer's requirements and all of utility Power's requirements are catered for.

Each overhead line requires different design considerations, configurations, layouts, etc. As such, there may be many different ways to approach a design.

The information contained in this blog will assist the designer to develop a structured design approach, and ensure that the optimum line configuration is selected at all times.


What Is Substation?

 A substation is a high-voltage electric system facility. It is used to switch generators, equipment, and circuits or lines in and out of a system. It also is used to change AC voltages from one level to another, and/or change alternating current to direct current or direct current to alternating current. Some substations are small with little more than a transformer and associated switches. Others are very large with several transformers and dozens of switches and other equipment. There are three aspects to substations:


Figure 1. Typical substation
Figure 1. Typical substation

Unity Power Factor

Unity Power Factor = 1. When the Power Factor of electrical loads is Unity or One, it means there are no reactive component in the Load like pure resistance in Incandescent Bulbs, Electric Stoves, Flat Iron, etc.

When the loads are inductive like Fluorescent Lights with Ballasts, Induction Electric Motors, etc., the Power Factor is less than Unity which may be in the range of 0+ to 0.9999+. This range of Power Factor is the Cosine of the Angle between the True Power WATTs and Active Power VA in the Power Triangle. The opposite side to the Angle represent the Reactive Load in VAR. The longer this side of VAR the poorer is the Power Factor as it approaches a Power Factor of 0+ which means the Active Power WATTs is being minimized to ZERO and no Energy or KWH is registered by the electric meter which is the basis of the Power Company to bill the consumer.

When the Power Factor of the Electric System is Unity, it means a very efficient Power Generation and Distribution System, however it is rarely achievable and nearly impossible. 

MicroGrid

 A microgrid is a small-scale power grid that can operate independently or in conjunction with the area's main electrical grid. Any small-scale localized station with its own power resources, generation and loads and definable boundaries qualifies as a microgrid.

A microgrid is an electrical system that includes multiple loads and distributed energy resources that can be operated in parallel with the broader utility grid or as an electrical island.

IEEE Std 1547.4-2011 defines Distributed Resource (DR) island systems or microgrids as Electric Power Systems (EPS) that:

(1) have DR and load,

(2) have the ability to disconnect from and parallel with the area EPS,

(3) include the local EPS and may include portions of the area EPS, and

(4) are intentionally planned.

Digital Fault Recorders (DFRs)

 

What is a fault recorder in power systems?

Digital fault recorders (DFRs) are multi-channel devices that are designed to capture and record the waveforms and sequence of events associated with power system faults. They come in many shapes and sizes and look similar to this one:


The waveforms they capture look like this:


AC 12V-0-12V transformer